(1) If blasting has been carried out at a blasting site during a working shift, work must not begin on the next working shift until the site has been inspected and declared safe by a shotfirer authorised to use explosives under the blasting permit for the operation.
(2) The shotfirer must tell the person responsible for control of the blasting site during the next shift of—
(a) the number and position of all blast holes that have been fired during the previous shift; and
(b) any suspected misfires.
Division 2.9.9 Electrical firing