(1) This regulation applies if—
(a) sanitary plumbing or sanitary drainage work has been inspected and approved; or
(b) an inspector has advised the person who did the work that an inspection is not required.
(2) A person who does sanitary plumbing or sanitary drainage work must, if satisfied that the work has been completed in accordance with these regulations and Australian Standard 3500, within 7 days after completion of the work, give the chief executive—
(a) a statement of the work completed; and
(b) evidence of payment of inspection fees under these regulations; and
(c) a copy of—
(i) if the work relates to a single residential building—a drainage plan on which there is endorsed a certificate that the plan is a true record of the work carried out; or
(ii) in any other case—an approved drainage plan on which there is endorsed a certificate that the plan is a true record of the work carried out.
Note A certificate of compliance for plumbing or sanitary drainage work cannot be issued under regulation 25 unless the chief executive is satisfied that the work complies with the regulations. The chief executive may only be able to be so satisfied if the statement, evidence and plan about the work has been given.