Australian Capital Territory Numbered Regulations

[Index] [Table] [Search] [Search this Regulation] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

WATER AND SEWERAGE REGULATIONS 2001 (2001 NO 2) - REG 19

Inspection of work etc

(1)       A person who does work on a water service or hot water system must tell the chief executive when the work is ready for inspection.

Maximum penalty: 10 penalty units.

(2)       A person who does work on a water service or hot water system must leave the work uncovered and convenient for inspection until whichever of the following happens first:

        (a)     the work is inspected and approved by an inspector;

        (b)     an inspector advises the person that an inspection is not required;

        (c)     the end of 2 working days after the chief executive was told that the work was ready for inspection.

Maximum penalty: 5 penalty units.