(1) A person who does sanitary plumbing or sanitary drainage work must tell the chief executive when the work is ready for inspection.
Maximum penalty: 10 penalty units.
(2) A person who does sanitary plumbing or sanitary drainage work must leave the work uncovered and convenient for inspection until whichever of the following happens first:
(a) the work is inspected and approved by an inspector;
(b) an inspector advises the person that an inspection is not required;
(c) if the work is sanitary plumbing work—the end of 2 working days after the chief executive was told that the work was ready for inspection.
Maximum penalty: 5 penalty units.
(3) A person who does sanitary plumbing or sanitary drainage work must, while the work is being done, keep on the premises a copy of the plan approval showing any minor variations to the approved plan.
Maximum penalty: 10 penalty units.