(1) A person may apply to the chief executive for a construction induction training card.
Note 1 If a form is approved under the Act, s 229 for this provision, the form must be used.
Note 2 A fee may be determined under the Act, s 228 for this provision.
(2) The person must make the application not later than—
(a) 60 days after the day the person receives a statement of attainment for construction induction training; or
(b) if the chief executive allows a later time—the later time.
(3) The application must be accompanied by the following:
(a) evidence of the applicant's identity and date of birth;
(b) a sample of the applicant's usual signature;
(c) the statement of attainment for construction induction training issued to the applicant;
(d) any other document or further information required in writing by the chief executive that the chief executive considers is relevant to the application.
(4) The chief executive may, by written notice given to an applicant, require the applicant to give the chief executive additional information or documents the chief executive reasonably needs to decide the application.