Industry Secretary must decide to grant or refuse application
(1) After considering the application, the * Industry Secretary must decide to either grant or refuse the application.
Criteria for grant of application
(2) The * Industry Secretary must not decide to grant an application unless he or she is satisfied that the design meets the criteria set out in the * approved occupational clothing guidelines.
Note: The approved occupational clothing guidelines are created under section 34 - 55.
When Industry Secretary taken to have refused application
(3) The * Industry Secretary is taken to have refused an application if he or she does not make a decision by the later of the following times (the deadline ):
(a) the end of 90 days (the 90 - day period ) after the day the Industry Secretary receives the application;
(b) if the Industry Secretary, by written notice given to the applicant within the 90 - day period, requests the applicant to give further information about the application--the end of 90 days after the Industry Secretary receives the further information.