Scope
(1) This section applies if:
(a) a cash - bid petroleum exploration permit expires; and
(b) the permit cannot be renewed.
Note: See section 120 (non - renewable permits) and section 121 (limit on renewal of permits).
Extension of permit--requirement to nominate blocks as location
(2) If, before the expiry of the permit:
(a) the Joint Authority had required the permittee to nominate, under section 130, a block or blocks in relation to which the permit was in force; and
(b) the permittee had not complied with the requirement;
the permit continues in force over that block or those blocks until the end of the period the permittee has to comply with the requirement.
Extension of permit--nomination of blocks as location, declaration of location
(3) If, before the expiry of the permit:
(a) a block or blocks in relation to which the permit was in force had been nominated under section 129; or
(b) both:
(i) a declaration under section 131 had been made in relation to a block or blocks in relation to which the permit was in force; and
(ii) the permittee had not requested that the declaration be revoked;
the permit continues in force over that block or those blocks until whichever of the following events happens first:
(c) a declaration under section 131 in relation to the block or blocks is revoked;
(d) a petroleum retention lease or a petroleum production licence is granted in relation to the block or blocks;
(e) the application period referred to in section 141 in relation to the block or blocks ends without the permittee making an application under that section for a petroleum retention lease in relation to the block or blocks;
(f) if the Royalty Act does not apply to the permit--the application period referred to in section 169 in relation to the block or blocks ends without the permittee making an application under section 168 for a petroleum production licence over the block or blocks;
(g) if the Royalty Act applies to the permit--the application period referred to in clause 3 of Schedule 4 in relation to the block or blocks ends without the permittee making an application under clause 2 of Schedule 4 for a petroleum production licence over the block or blocks.
(4) This section has effect subject to this Chapter but despite section 102.