If an applicant for certification of a facility fails to provide information required under the Act, section 85 (1) within the period stated in a notice given under the Act, section 85 (2) and gives no reasonable explanation for the failure, the regulator may refuse to certify the facility.
Note A refusal to certify a facility is a reviewable decision (see the Act, div 12.2).