AUSTRALIAN JOBS ACT 2013 - SECT 21

Duration of approved AIP plan

Project involves establishing a new relevant facility

  (1)   If a major project involves establishing a new relevant facility, an approved AIP plan for the project:

  (a)   comes into force when the Authority approves the plan; and

  (b)   subject to this Division, continues in force until the end of the 2 - year period beginning when the project is completed.

Project does not involve establishing a new relevant facility

  (2)   If a major project does not involve establishing a new relevant facility, an approved AIP plan for the project:

  (a)   comes into force when the Authority approves the plan; and

  (b)   subject to this Division, continues in force until the project is completed.