Commonwealth Consolidated Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

OFFSHORE ELECTRICITY INFRASTRUCTURE ACT 2021 - SECT 138

When a determination takes effect

  (1)   A determination of a safety zone takes effect at the time specified in the determination.

  (2)   If a determination relates only to offshore renewable energy infrastructure or offshore electricity transmission infrastructure that is not yet installed, the Regulator must not specify a time before the time that the Regulator is satisfied that installation of the infrastructure will begin.



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback