OFFSHORE ELECTRICITY INFRASTRUCTURE ACT 2021 - SECT 146

When a determination takes effect

  (1)   A determination of a protection zone takes effect at the time specified by the Regulator.

  (2)   If a determination relates only to offshore renewable energy infrastructure or offshore electricity transmission infrastructure that is not yet installed, the Regulator must not specify a time before the time that the Regulator is satisfied that installation of the infrastructure will begin.